Net Zero Teesside (NZT) Details
1. Key Information
| Field | Information |
|---|---|
| Project ID | 962 |
| Project Name | Net Zero Teesside (NZT) |
| Alternative Name | Teesside Collective Industrial CCS Project |
| Scale | Commercial |
| Purpose | Industry |
| Location | Teesside |
| Country | UK |
| Continent | Europe |
| Latitude | 54.565195 |
| Longitude | -1.306205 |
| Regulation Status | |
| Primary Company / Alliance | Net Zero Teesside (NZT) Partnership |
2. Further Information
| Field | Information |
|---|---|
| Project Description | Successor to the Teesside Collective industrial CCS project. Relaunched as Net Zero Teesside (NZT) in October 2019, following the formation of the Oil and Gas Climate Initiative's (OGCI ) Clean Gas Project - now Net Zero Teesside Power Station (NZT Power) - in 2018. With NZT Power (see separate entry), a large, new gas-fired power station near the former SSI steelworks site, as the anchor project, NZT proposes a CO2 collection network with up to 10MtCO2/yr capacity. The CO2 will be stored in the Endurance aquifer in the Southern North Sea as part of the Northern Endurance Partnership (NEP), with Zero Carbon Humber (ZCH). Together, NZT, ZCH and the NEP form the East Coast Cluster. The East Coast Cluster was selected as a ‘Track-1’ cluster in the UK Government’s CCUS Cluster Sequencing Track 1 projects announcement (Oct 2021). Map location is the Tees Valley Collective Authority office. |
| Project Website | https://www.netzeroteesside.co.uk/ |
3. Status
| Field | Information |
|---|---|
| Status | In Design |
| Status Comment | Feasibility studies complete. A Development Consent Order (‘DCO’) application was submitted to the Planning Inspectorate in summer 2021. |
| Intended Operational Year | 2026 |
| Operation Year | |
| End Operation Year | |
| Date Comment |
4. Funding
| Field | Information |
|---|---|
| Estimated Cost | |
| Public Funding | Yes |
| Public Funding Comment | GBP 34M through City Deal, GBP 1 M for pre-FEED feasibility study, GBP 3.8 for conceptual design study. Received GBP 28M (Mar 2021) for infrastructure components in Phase 2 of the UKRI Industrial Strategy Challenge Fund (ISCF) and Phase 1 funding of between GBP 60-200k. The related Net Zero Tees Valley Cluster Plan also received a share of the GBP8M ISCF Phase 2 funding (Jan 2021) and Phase 1 funding of between GBP 40-120k (Apr 2020). |
| Public Engagement | Numerous public consultations between Oct 2019-Jan 2021, and much more under the Teesside Collective project |
5. Organisation
| Field | Information |
|---|---|
| Non Commercial Org | Tees Valley Combined Authority (TVCA) |
| CCS Group | |
| Company Comment | NZT Power, BOC, CF Fertilizers, Kellas, H2Teesside (bp), Suez, TV ERF, 8 Rivers |
6. Storage
| Field | Information |
|---|---|
| Fate | Saline Formation |
| On / Offshore | Offshore |
| Storage Company | Northern Endurance Partnership (NEP) |
| Injection (MT CO2/yr) | 2.0 |
| Total Injection (MT CO2) | |
| Storage Distance | 145km |
| Storage Country | UK |
| Storage Latitude | |
| Storage Longitude | |
| Storage Comment | 2Mt/yr is for the anchor NZT Power project only. Endurance aquifer, as part of Northern Endurance Partnership; 8.25Mt/yr by 2030 |
| Storage Monitoring |
7. Production
| Field | Information |
|---|---|
| Product | Electricity, ammonia, hydrogen, PET, other industrial products and services |
| Source Company | NZT Power, BOC, CF Fertilizers, Kellas, H2Teesside (bp), Suez, TV ERF, 8 Rivers |
| Construction | New |
| Permit | |
| Permit Date | |
| Feedstock | Other |
| Feedstock Detail | Gas at NZT Power, BOC, CF Fertilizers, Kellas, H2Teesside (bp), Suez and 8 Rivers; municipal waste at Suez and TV ERF |
| Feedstock Additional | |
| Power Plant Size | |
| Fuel Capacity | |
| Production Capacity | |
| Plant Capacity Comment | NZT Power |
8. Separation
| Field | Information |
|---|---|
| Separation Type | Unknown |
| Separation Technology | |
| Separation Comment | Mostly post-combustion; pre-combustion on hydrogen production |
| Capture Company | |
| CCS Capacity |
9. Transport
| Field | Information |
|---|---|
| Transport Method | Ship |
| Transport Company | Northern Endurance Partnership (NEP) |
| Cluster | Yes |
| Cluster Comment | Net Zero Teesside cluster and East Coast Cluster |
| Trans-boundary | No |
| Transport Comment |
10. Edit History
| Field | Information |
|---|---|
| Date Entered | 2013-12-16 09:35:17 |
| Entered by | CCSDBA |
| Date Modified | 2021-11-03 17:28:35.381652 |
| Modified by | rsteven2 |
Links
| http://www.teessidecollective.co.uk/teesside-collective-blueprint-for-industrial-ccs-in-the-uk/ |
| Teesside Collective Reports - Blueprint for Industrial CCS in the UK (all published reports) |
| https://www.alpekpolyester.co.uk/wp-content/uploads/2020/01/Alpek-Polyester-UK-Ltd-Press-Release-ENG-1-3-20-V6.pdf |
| Press release (Jan 2020): Lotte Chemicals acquired by Alpek Polyester. |
| https://www.ukri.org/news/ukri-announces-winners-of-industrial-cluster-competition/ |
| UKRI Press Release (Jan 2021): ISCF Cluster Plan Phase 2 funding awards announcement |
| https://www.ukri.org/news/ukri-awards-171m-in-uk-decarbonisation-to-nine-projects/ |
| UKRI Press Release (Mar 2021): ISCF Deployment Project Phase 2 funding awards announcement |
| https://questions-statements.parliament.uk/written-statements/detail/2021-10-19/hcws325 |
| UK Parliament (Oct 2021): UK’s CCUS Cluster Sequencing Process Track 1 projects announcement |
| https://www.netzeroteesside.co.uk |
| Net Zero Teesside (NZT) |