C4 – Carbon Capture Cluster Copenhagen Details
1. Key Information
| Field | Information |
|---|---|
| Project ID | 2731 |
| Project Name | C4 – Carbon Capture Cluster Copenhagen |
| Alternative Name | C4 or Carbon Capture Cluster Copenhagen |
| Scale | Demonstration |
| Purpose | Power |
| Location | Copenhagen Metropolitan area |
| Country | Denmark |
| Continent | Europe |
| Latitude | 55.684497 |
| Longitude | 12.616655 |
| Regulation Status | |
| Primary Company / Alliance | ARC, Argo, BIOFOS, Copenhagen Malmö Port (CMP), CTR, HOFOR, Vestforbrænding, VEKS and Ørsted |
2. Further Information
| Field | Information |
|---|---|
| Project Description | The project aims to reduce CO2 emissions by ~3Mt/yr from large power plants in the Copenhagen metropolitan area along with utilisation and communal CO2 transport and geological storage options in the Danish North Sea. The plants include the ARC Amager Bakke, Vestforbrænding and Argo waste-to-energy plants, the HOFOR biomass plant and the BIOFOS wastewater sludge incinceration plant. More than half of the expected CO2 captured will come from biogenic sources, therefore effecting carbon dioxide removal from the atmosphere. Current map location is arbitrary, given that this is a multi-partner cluster project. |
| Project Website | https://www.c4cph.dk/en/ |
3. Status
| Field | Information |
|---|---|
| Status | In Planning |
| Status Comment | A political strategy is expected in late 2021 |
| Intended Operational Year | 2025 |
| Operation Year | |
| End Operation Year | |
| Date Comment | Intended operational year was 2025; currently no fixed schedule for the project following lack of financial support for the Amager Bakke EfW plant CCS project |
4. Funding
| Field | Information |
|---|---|
| Estimated Cost | |
| Public Funding | No |
| Public Funding Comment | |
| Public Engagement |
5. Organisation
| Field | Information |
|---|---|
| Non Commercial Org | |
| CCS Group | |
| Company Comment | ARC, Argo, BIOFOS, Copenhagen Malmö Port (CMP), CTR, HOFOR, Vestforbrænding, VEKS and Ørsted |
6. Storage
| Field | Information |
|---|---|
| Fate | Depleted Oil and Gas |
| On / Offshore | Offshore |
| Storage Company | |
| Injection (MT CO2/yr) | 3.0 |
| Total Injection (MT CO2) | |
| Storage Distance | |
| Storage Country | Denmark |
| Storage Latitude | |
| Storage Longitude | |
| Storage Comment | Offshore storage and utilisation are being considered |
| Storage Monitoring |
7. Production
| Field | Information |
|---|---|
| Product | Power, heat (district heating), water |
| Source Company | ARC Amager Bakke, Vestforbrænding and Argo waste-to-energy plants, HOFOR biomass plant, BIOFOS wastewater sludge incinceration plant |
| Construction | Unknown |
| Permit | |
| Permit Date | |
| Feedstock | Other |
| Feedstock Detail | Residual minicipal waste, biomass, biogenic waste |
| Feedstock Additional | |
| Power Plant Size | |
| Fuel Capacity | |
| Production Capacity | |
| Plant Capacity Comment |
8. Separation
| Field | Information |
|---|---|
| Separation Type | Unknown |
| Separation Technology | |
| Separation Comment | |
| Capture Company | |
| CCS Capacity |
9. Transport
| Field | Information |
|---|---|
| Transport Method | Pipe and Ship |
| Transport Company | |
| Cluster | Yes |
| Cluster Comment | |
| Trans-boundary | No |
| Transport Comment | Potential transport options include onshore pipe network with offshore shipping from the port of Prøvestenen to geological storage |
10. Edit History
| Field | Information |
|---|---|
| Date Entered | 2021-10-21 16:44:15.161960 |
| Entered by | rsteven2 |
| Date Modified | 2023-06-02 12:49:48.091347 |
| Modified by | rsteven2 |
Links
| https://a-r-c.dk/app/uploads/2021/02/C4-press_release.pdf |
| ARC (Feb 2020): Press Release |
| https://www.endswasteandbioenergy.com/article/1796599/withdrawal-efw-css-funding-ends-copenhagens-2025-climate-neutral-hopes?bulletin=ewb-weekly&utm_medium=EMAIL&utm_campaign=eNews%20Bulletin&utm_source=20220830&utm_content=EWB%20Waste%20and%20Bioenergy%20Weekly%20(41)::&email_hash= |
| ENDS (Aug 2022): Withdrawal of EfW from CCS funding ends Copenhagen’s 2025 climate-neutral hopes |